PKSP · DCC

پیش‌نمایش امن سند

PSR-FOREIGN 1405.03.19.xlsx

زارچ .XLSX 125,249 B 2 صفحه طبقه‌بندی: normal
این قالب در مرورگر نمایش بومی قابل اتکا ندارد؛ متن استخراج‌شده برای مشاهده آنلاین نشان داده شده و اصل فایل بدون تغییر قابل دانلود است.
بخش 1 · منبع متن xlsx · 3,686 نویسه
[Sheet: Rev-0]
Procurement Status Report ( نیروگاه خورشیدی 20 مگاواتی )    																												REV: 4				Cut off Date:			1405/03/19				0.2	0.2	0.2	0.2	0.2	Before P.O Progress	0.1	0.05	0.15	0.45	0.1	0.1	0.05	After P.O Progress
Item	MR No.	MR Description	PRODUCT MODEL	Discipline	PI No.	QTY	UNIT	QTY/PALLET	PALLET/40' HC	CONTAINER TYPE	TOTAL CONTAINERS	MR Release Date	Rev	MR Status	RFQ Sent (Tender)	Bid Close Date	TBE Issued Date	CBE Issued Date	PI UNIT PRICE	P.I TOTAL PRICE	P.I. Information Date		Vendor Information			Delivery Condition		K.O.M Date	P.I.M Date	ITP/ MPS Approved (Starting)	Inspection Information	Delivery Dates				Delivery Information	Current Status	Area of Concerns	Inquiry	TCL	TBE	Bid Winner	PO %		Engineering
Progress	Material Suborder Progress	Material Receipt
Progress	Manufacturing Progress	IRN Progress	MRS Progress	Final Book
																					P.I Signed with Vendor	Advance Payment Completion Date	Vendor Name	Manufacturer (Brand)	Origin	Duration	Term					At Site (Esimate)	At Port of Destination (Estimate)	At Site Actual	At Port of Destination (Actual)
1	--	SOLAR MODULE	TRINA SOLAR NEG21C.20	Electrical	JQI-1003	4752	PCS	33	18	40' HC	8	1404/10/22	--	--	1404/10/26	1404/10/29	1404/11/01	1404/11/02	82.49	391992.48	1404/10/20	1404/11/16	JINQI SOLAR	TRINA SOLAR	CHINA	IN STOCK	CIF 	1404/10/30	1404/11/15	Approved	Passed	1405/04/25	1405/04/10			The goods are being stored at Jebel Ali warehouse and waiting for a new shipment to Bandar Abbas.	Jebel Ali (Dubai), UAE	U.S. Army Blockade	1	1	1	1	1	=SUMPRODUCT($AN$1:$AR$1,AN4:AR4)	1	1	1	1	1			=SUMPRODUCT($AT$1:$AZ$1,AT4:AZ4)
2	--	SOLAR MODULE	TRINA SOLAR NEG21C.20	Electrical	JQI-1003	5940	PCS	33	18	40' HC	10	1404/10/22	--	--	1404/10/26	1404/10/29	1404/11/01	1404/11/02	82.49	489990.6	1404/10/20	1404/11/16	JINQI SOLAR	TRINA SOLAR	CHINA	IN STOCK	CIF 	1404/10/30	1404/11/15	Approved	Passed	1405/04/25	1405/04/10			The goods are being stored at Jebel Ali warehouse and waiting for a new shipment to Bandar Abbas.	Jebel Ali (Dubai), UAE	U.S. Army Blockade	1	1	1	1	1	=SUMPRODUCT($AN$1:$AR$1,AN5:AR5)	1	1	1	1	1			=SUMPRODUCT($AT$1:$AZ$1,AT5:AZ5)
3	--	SOLAR MODULE	TRINA SOLAR NEG21C.20	Electrical	JQI-1003	17226	PCS	33	18	40' HC	29	1404/10/22	--	--	1404/10/26	1404/10/29	1404/11/01	1404/11/02	82.49	1420972.74	1404/10/20	1404/11/16	JINQI SOLAR	TRINA SOLAR	CHINA	IN STOCK	CIF 	1404/10/30	1404/11/15	Approved	Passed	1405/04/01	1405/04/10			16X40' containers are moving from Zhuhai Port to Bandar Abbas. Bill of Lading is provided to MC.
13X40' containers are moving from Zhuhai Port to Bandar Abbas. Bill of Lading is provided to MC.
MC: After arrival at port, 10-15 days for discharge. 2 days for transit.	On Freight to Bandar Abbas	U.S. Army Blockade	1	1	1	1	1	=SUMPRODUCT($AN$1:$AR$1,AN6:AR6)	1	1	1	1	1			=SUMPRODUCT($AT$1:$AZ$1,AT6:AZ6)
4	--	INVERTER	SOLIS - 350 6 MPPT INVERTER	Electrical	JQI-1003	62	PCS	1	62	40' HC	1	1404/05/11	--	--	1404/11/09	1404/11/13	1405/01/08	1405/01/09	10500	651000	1404/10/20	1404/11/16	JINQI SOLAR	SOLIS	CHINA	60 WORKING DAYS	CIF 	1404/10/30	Pending	Pending		1405/05/16	1405/05/01			-	Production Finished -Waiting on Documents for Inspection		1	1	1	1	1	=SUMPRODUCT($AN$1:$AR$1,AN7:AR7)	1	1	1	1				=SUMPRODUCT($AT$1:$AZ$1,AT7:AZ7)
5	--	MV STATION	SOLIS - 6500 KVA MV STATION	Electrical	JQI-1003	3	PCS	1	1	20' HD	3	1404/29/11	--	--	1404/12/03	1404/12/06	1405/01/08	1405/01/09	193000	579000	1404/10/20	1404/11/16	JINQI SOLAR	SOLIS	CHINA	90 WORKING DAYS	CIF 	1404/10/30	Pending	Pending		1405/08/30	1405/08/15			Delivery time based on ABB
ABB Procurement time : 12 Weeks	Under Production 		1	1	1	1	1	=SUMPRODUCT($AN$1:$AR$1,AN8:AR8)	1	1	1	0.4				=SUMPRODUCT($AT$1:$AZ$1,AT8:AZ8)
بخش 2 · منبع متن xlsx · 704 نویسه
[Sheet: Report]
Discipline	Total MR	Issued MR	TBE	P.O	RawMat.	Manufac.	I.R.N	Delivery to Site
Piping
Mechanical
Pipeline
Instrument
Electrical	5	N/A	5	5	5	5	3
Safety
Telecom
Process
Architectural
MR Description	Report
SOLAR MODULE
(QTY 4752)	تعداد 18 کانتینر در انبار جبل علی + 29 کانتینر در تاریخ 1405/03/06 به مقصد بندرعباس حمل گردید
SOLAR MODULE
(QTY 5940)
SOLAR MODULE
(QTY 17226)
INVERTER	 ساخت تکمیل شده و در انتظار معرفی بازرس کارفرما جهت بازرسی و مجوز حمل می باشد.
MV STATION	تاریخ پیش بینی پایان ساخت و بازرسی طبق مکاتبات با چین ، اواسط تیر ماه 1405 و پیش بینی حمل اواسط شهریور ماه 1405 می باشد.
در صورت انتخاب برند ABB ، پیش بینی ساخت و حمل اواسط آبان ماه 1405 می باشد. (MC: برند ABB انتخاب شد)