صفحه 1 · xlsx · 5,144 نویسه
page_id=7355 / file_id=2620
[Sheet: 1] Procurement Status Report ( نیروگاه خورشیدی 20 مگاواتی ) Cut off Date: 2026-05-19 00:00:00 Item MR No. MR Description Discipline PO No. QTY Unit MR Release Date Rev MR Status RFQ Sent (Tender) Bid Close Date TBE Issued Date CBE Issued Date Board committee Approval Date Work Commencement Letter Date PO Price P.O. Information Date Vendor Information Delivery Condition K.O.M Date P.I.M Date ITP/ MPS Approved…
2.Project\01 - Zarch\05.Planning & Control\02.Progress Reports\Weekly Report\پیمانکار نیروگاه\1405.02.29\14050229 W - 01\Procurement Status Report-(EPC)1405.02.29.xlsx · page 1